Creating a Dynamic Link or Linked Fields in Project 2013.
- Copy a normal cell (Ctrl+C)
- Right click on the cell you want to paste the copied information
- Select Paste Special
- Select Paste Link and then OK
- Change the value of the source cell,
- in my case I just changed the duration to 5 days, which changed the finish date as well
- you will see the value of the dynamic cell changing automatically
- magic!!! :)
Seems that we can use this in many different cases… :)
Thanks for Alexandre Paiva in this post: http://gerentedeprojeto.net.br/?p=8360